Dump-Turned-Park on Staten Island Faces Delays
The Parks Department is investigating the problem, which was brought to its attention last week when the contractor in charge of building Owl Hollow Fields, a 21-acre lot that will include athletic fields, a picnic area and hiking trails, complained that the crushed rock it had laid down as foundation had been sinking significantly.
A project manager for the contractor, D. Gangi Contracting, confirmed that the project is on hold.
Workers began laying foundation fill in October 2009 and noticed last year the materials appeared to be sinking, according to the New York Post.
The city and the contractor are now reportedly arguing over who's responsible.
The cost of the project was originally $6.8 million and has ballooned to $14 million.
The Parks Department said in a statement that it is "sending out a crew of surveyors this week to document the current grades."
"Other surveys will be taken over the next two to three months," the department said. "After the subsequent surveys are taken, the data will be reviewed to determine if there is a settlement problem."